Andover Town Planner Lisa Schwarz has released the summer schedule for the Main Street (Route 28) construction project.

Work this week included pouring concrete sidewalks at Elm Square, Old Andover Village and Harding Street; installing new traffic signals at Elm Square; and paving North Main Street with a top coat of asphalt.

Drainage work on Chestnut Street was also expected to wrap up. Any unfinished work this week is expected to carry over into next week.

Here is the remaining project schedule:

Week of June 15-19: Install curbing and sidewalks at intersection of Chestnut and Main streets
Travel lanes will be striped on North and South Main streets

Week of June 22-26: Complete sidewalks north of Memorial Hall Library
Complete sidewalk in front of Natale’s Men’s Clothier, 1-7 Main Street

Week of June 29-July 2: Install rumble medians and flush granite at crosswalks

Mid-July: Pour top coat throughout the downtown and install remaining crosswalks

End-July/August: Install signage

Fall 2009: Install remainder of trees and landscaping